Heat pump installation timeline

Heat pump installation timeline in Ireland, including survey, system design, SEAI grant approval, preparation work, on-site installation, commissioning and household disruption.

Typical on-site installation: 2–4 days | Full process: 3–6 weeks

From Survey to Commissioning

The physical installation of an air-to-water heat pump usually takes only a few days, but the full process starts earlier with a technical survey and system design.

The typical sequence is survey → heat-loss calculation → quotation → grant approval → preparation → installation → commissioning → post-works documentation.

The source page gives a typical full project period of 3–6 weeks.

Survey & Design Stage

Survey & Design Stage

Technical survey: typically 1–2 hours

System design and quotation: 1–2 weeks

SEAI grant approval: typically 1–3 weeks

The survey checks insulation, radiator sizing, electrical capacity and outdoor-unit location.

Preparation & Installation

Preparation Work

Radiator replacement, cylinder upgrades, electrical-board work and pipe changes may be required.

Typical preparation duration: 1–3 days depending on scope.

On-Site Installation

Small house: 2–3 days

Semi-detached: 2–4 days

Detached: 3–5 days

Typical Project Timeline

StageTypical Duration
Initial consultation1 week
Survey & heat-loss calculation1 week
Grant approval1–3 weeks
Installation works2–4 days
Commissioning & documentation1 week

Total project duration: typically 3–6 weeks.

Household Disruption

Household Disruption

Most disruption happens while the existing boiler system is removed and new pipework, cylinder and electrical connections are installed.

Typical disruption includes temporary loss of heating and hot water, drilling noise and access to utility or plant areas.

The source page gives a typical disruption period of 1–3 days.

Installation & Commissioning Detail

TaskTypical Duration / Note
Outdoor unit installation4–6 hours
System commissioning2–4 hours
Heating-system integrationCompleted during main install
Post-works BERRequired for SEAI grant documentation

Commissioning includes pressure testing, electrical safety testing, flow-temperature calibration and control setup.

Planning the Programme

Before Installation

Do not schedule the physical installation before required SEAI grant approval.

Complete radiator, cylinder or electrical preparation first where practical.

During Installation

Allow for 1–3 days of heating/hot-water disruption.

Ensure access to the plant area and outdoor-unit route.

After Installation

Commissioning certificate, electrical completion certificate, warranty and post-works BER documentation are required.

These documents support the grant claim.

Heat pump summary

Summary

Most air-to-water heat-pump installations require around 2–4 days of on-site work.

The complete process from initial consultation to commissioning typically takes 3–6 weeks.

Most household disruption is concentrated into the 1–3 day period when the old heating system is disconnected and the new system is integrated.

Other resources:

Air-to-Water Heat Pump Costs

SEAI Heat Pump Grant Explained

Required Upgrades – Before Installation

Radiators vs Underfloor Comparison

Electricity Running Costs

BER Requirements for Eligibility

Payback Period vs Oil or Gas