Home » Heating Pumps » Installation Timeline and Disruption (2026)

Installation Timeline and Disruption (2026)

Installation timeline and disruption for heat pump systems in Ireland (2026), including survey stages, installation duration and typical household disruption during works.


1. Overview

Installing an air-to-water heat pump involves both plumbing and electrical work.

Although the system installation itself is usually completed within a few days, the full process from survey to commissioning can take several weeks.

The overall timeline typically includes:

Home energy assessment
System design and heat loss calculation
SEAI grant approval
Installation and commissioning

Most installations involve moderate disruption to heating and hot water services during the installation period.


2. Pre-Installation Survey

Before installation begins, the installer carries out a technical survey.

This typically includes:

Heat loss calculation
Assessment of insulation levels
Radiator sizing evaluation
Electrical system inspection
Outdoor unit location planning

Survey duration typically ranges:

1 – 2 hours.

The survey determines the correct heat pump size and identifies any upgrades required.


3. System Design and Grant Approval

Following the survey, the installer prepares a system design and quotation.

This stage may include:

Heat loss calculation report
System sizing calculations
Radiator upgrade recommendations
Grant eligibility confirmation

Typical timeframe:

StageDuration
System design and quotation1 – 2 weeks
Grant application approval1 – 3 weeks

Installation should not begin until grant approval is received.


4. Preparation Work

Some homes require preparatory work before installation begins.

Preparation tasks may include:

Radiator replacement
Hot water cylinder upgrade
Electrical board upgrades
Pipework adjustments

Preparation work may take:

1 – 3 days depending on the scope of upgrades required.


5. Heat Pump Installation

The main installation stage involves several steps.

Typical installation tasks include:

Removing the existing boiler
Installing the heat pump outdoor unit
Installing the hot water cylinder
Connecting pipework and electrical systems
Installing system controls

Installation duration typically ranges:

Property TypeInstallation Time
Small house2 – 3 days
Semi-detached house2 – 4 days
Detached house3 – 5 days

Installation time varies depending on system complexity.


6. Outdoor Unit Installation

The outdoor heat pump unit must be mounted in a suitable location.

Installation typically involves:

Installing a concrete base or wall bracket
Connecting refrigerant and water pipework
Electrical connection to the house

Typical installation time:

4 – 6 hours.

Adequate airflow space must be maintained around the unit.


7. Heating System Integration

The new heat pump must be integrated with the existing heating distribution system.

Integration tasks include:

Connecting radiators or underfloor heating
Installing circulation pumps
Balancing the heating system

This stage ensures heat is distributed evenly throughout the property.


8. System Commissioning

Once installation is complete, the system is commissioned.

Commissioning includes:

System pressure testing
Electrical safety testing
Flow temperature calibration
Control system configuration

Commissioning typically takes:

2 – 4 hours.

The installer ensures the system operates correctly before handover.


9. Disruption During Installation

Some disruption is expected during installation.

Typical disruption includes:

Temporary loss of heating and hot water
Access required to utility rooms or plant rooms
Noise from drilling and pipework installation
Temporary removal of the existing boiler system

Most homes experience disruption for:

1 – 3 days during installation.


10. Post-Installation Certification

After installation, several documentation steps are required.

Typical documentation includes:

System commissioning certificate
Electrical completion certificate
Warranty documentation
Post-works BER assessment

These documents are required to claim the SEAI grant.


11. Example Project Timeline

Typical heat pump project timeline:

StageTypical Duration
Initial consultation1 week
Survey and heat loss calculation1 week
Grant approval1 – 3 weeks
Installation works2 – 4 days
Commissioning and documentation1 week

Total project duration typically ranges:

3 – 6 weeks.


12. Typical Installation Timeline Summary

Air-to-water heat pump installation usually requires:

2 – 4 days of on-site installation work.

The complete project process from initial consultation to commissioning typically ranges:

3 – 6 weeks.

Most disruption occurs during the installation stage when the existing heating system is replaced.


13. Other Resources

Air-to-Water Heat Pump Costs

SEAI Heat Pump Grant Explained

Required Upgrades – Before Installation

Radiators vs Underfloor Comparison

Electricity Running Costs

BER Requirements for Eligibility

Payback Period vs Oil or Gas